Norcross Contruction Photos in Chronological Order
January 20: COMPLETED OFFICE!!....All Other photos in Chronological Order Showing Contruction Progress
Dawson Blvd Before Begin of Construction
Preparing Stained Flooring before Construction
June 2021 Leasing Offices Framed
November 2021 Sheetrock Hanging
Mudding Sheetrock December 2021
December 2021 Hanging Sheetrock
Painting Begins December 16, 2021
December 23 - Painting door frames with strong oil based enamel paint
Installing Door Frames Begins - December 17, 2021
December 28 - Ceiling Grid installation begun
Painted Door Frames.....Ready for Door hanigning
January 2....FIRST completed office
Offices Large enough for 2 Chairs
Some Offices with Glass Doors....All Offices with Keypad Door Locks
January 12 - Installation of Baseboard & Crown molding
January 15 - Installation of Mailboxes
January 16 - Mailbox Installation Work into the night to Finish!!
January 20 - Floors Cleaned....Building floor features modern look with stained concrete floors
January 20 Completed Office!